Balsham Play Park Upgrade 2021

Kompan is the company chosen to install our new play park. The old equipment is scheduled to be removed on the 25th January 2021 with the new equipment arriving on site on the 28th January.

This will take a couple of weeks to install with the wet pour and grass matting being installed around the 15th February.

Final completion is expected on the 22nd February.  However, due the weather there may be a slight delay in the project being completed.

All of the old equipment will be removed off site and taken away. The Parish Council cannot allow for any equipment to be removed by any members of the public.

All of the old equipment will be removed off site and taken away. The Parish Council cannot allow for any equipment to be removed by any members of the public.

Update 19th February 2021

There will be a delay to the completion of the play park by a week, so completion date will be 26th February. The Parish Council may delay opening up the play park until mid-March to allow the ground to dry before letting people use the equipment.

Update March 2021
The new playground is now open! Thank you for your patience while it was under construction.

Photos week by week:

End of week one (25th to 31st January 2021)

End of week two (1st to 7th February 2021)

End of week 3 (8th to 14th February 2021)

End of week 4 (15th to 21st February 2021)

Winning Design from Kompan

Adult Fitness Equipment
The Parish Council is currently looking into some adult fitness equipment pieces.

Upcoming Events

Recent News